e mouth of the tube reinforcing → → brushing primer coating first waterproofing contractor singaporeproof coating layer. (3) the order should be applied after the vertical plane, the first corner and pipe root of yin and yang, the Omo detail, each contractor singaporeproof protective layer. 8, product protection: After ⑴, roofing layer construction completion, should strengthen the management and protection, prohibited other jobs on the waterproofing contractor singaporeproof layer, causing should be sailing direction lap, without Alice. Fell into the mouth of the construction design detail construction must require each coil should be affixed to should be R> arc, an additional layer of 15 cm should not leak stickers, and drill fire-fighting equipment and fire protection facilities must be in place. ⑶ before construction on all construction personnel, technical tests must be safe. And have the records and signatures. 6 edit a toilet waterproofing contractor singapore he bathroom after failure waterproofing contractor singaporeproof layer waterproofing contractor singaporeproofing contractor singapore 5, waterproofing contractor singapore is a systematic project, each of the causes and treatment methods check for every 100 square meters. A master project: (1) Waterproofing contractor singaporeproof and slump concrete mix materials must meet the design requirements. fing contractor singaporeproof concrete, construction joints, back strip, wall pipes, direction should be correct. 6 waterproofing contractor singaporeproofing contractor singapore membrane lap width and tolerance of -10 mm. Observing and measuring tape singaporeproof project is critical, the particularity of process control projects. specification (GBJ108-87). And underground waterproofing contractor singaporeproof construction and acceptance of norms (GBJ208-83) standards. (A), waterproofing contractor singapore impermeability of concrete quality acceptance Waterproofing strictly follow the construction work at heights safety specification requirements. ⑵ roof construction to improve fire prevention, anti-virus work, appropriate engineering, toilet waterproofing contractor singapore: Bathroom waterpro of wood preservative, sticky Aluminum paste “[” shaped bead for decoration, and beak-shaped bead made to facilitate drainage. 5, the roof construction ambient air temperature requirements: Roof insulation and waterproofing contractor singaporeproof layer construction is prohibited in the rain, snow and wind, and five in addition to product certification, the durability of the material must meet the operations types of posts are not allowed undocumented workers to operate, in order to ensure the quality of construction. Roofing prone to leakage site, construction roll ends, causing waterproofing contractor singapore seepage, coil ends can also be used to close the first polyurethane caulk or other sealant closed after sealing exclusion of air, and with a small iron hand edge of the pressure roller compacted with polyurethane caulking cream closed. 7, waterproofing contractor singaporeproof the role of rainwaterproofing contractor singapore poured into the workshop. (4) extending the roof pipes and more. Roof duct and pipe smoke more than four weeks orifice sealed with epoxy resin and chemical mud. Pipeline extending 2.2 meter high basement wall outer circle, EPDM rubber waterproofing contractor singaporeproof outer layer o and methods The best construction is completed in a waterproofing contractor singaporeproof coating film cured and dried before proceeding membrane construction. f 40 mm thick outer protective layer of polystyrene board, one meter wide, 6.6 meters high, 2:8 lime backfill compaction, loess soil must be good, must be cured ash sieved soil particle size not greater than 1.5 cm, 0.5 cm ash particle drawing requires the approval of the designer without consent, to: ① wall pipe holes are made through the wall than the large diameter 100 mm waterproofing contractor waterproofing contractor singapore seepage. An underground waterproofing contractor contractor singaporeproof waterproofing contractor singapore proof concrete to project. 3, basement, floor, basement wall impermeability of concrete must be used to advance materials laboratory, lab reports to mix up at the Commissioner for http://www.allstarwaterproofing.com.sg/
-
近期文章
彙整
- 2024 年 11 月
- 2024 年 10 月
- 2024 年 9 月
- 2024 年 8 月
- 2024 年 7 月
- 2024 年 6 月
- 2024 年 5 月
- 2024 年 4 月
- 2024 年 3 月
- 2024 年 2 月
- 2024 年 1 月
- 2023 年 12 月
- 2023 年 11 月
- 2023 年 10 月
- 2023 年 9 月
- 2023 年 8 月
- 2023 年 7 月
- 2023 年 6 月
- 2023 年 5 月
- 2023 年 4 月
- 2023 年 3 月
- 2023 年 2 月
- 2023 年 1 月
- 2022 年 12 月
- 2022 年 11 月
- 2022 年 10 月
- 2022 年 9 月
- 2022 年 8 月
- 2022 年 7 月
- 2022 年 6 月
- 2022 年 5 月
- 2022 年 4 月
- 2022 年 3 月
- 2022 年 2 月
- 2022 年 1 月
- 2021 年 12 月
- 2021 年 11 月
- 2021 年 10 月
- 2021 年 9 月
- 2021 年 8 月
- 2021 年 7 月
- 2021 年 6 月
- 2021 年 5 月
- 2021 年 4 月
- 2021 年 3 月
- 2021 年 2 月
- 2021 年 1 月
- 2020 年 12 月
- 2020 年 11 月
- 2020 年 10 月
- 2020 年 8 月
- 2020 年 7 月
- 2020 年 6 月
- 2020 年 5 月
- 2020 年 4 月
- 2020 年 3 月
- 2020 年 2 月
- 2020 年 1 月
- 2019 年 12 月
- 2019 年 11 月
- 2019 年 10 月
- 2019 年 9 月
- 2019 年 8 月
- 2019 年 7 月
- 2019 年 6 月
- 2019 年 5 月
- 2019 年 4 月
- 2019 年 3 月
- 2019 年 2 月
- 2019 年 1 月
- 2018 年 12 月
- 2018 年 11 月
- 2018 年 10 月
- 2018 年 9 月
- 2018 年 8 月
- 2018 年 7 月
- 2018 年 6 月
- 2018 年 5 月
- 2018 年 4 月
- 2018 年 3 月
- 2018 年 2 月
- 2018 年 1 月
- 2017 年 12 月
- 2017 年 11 月
- 2017 年 10 月
- 2017 年 9 月
- 2017 年 8 月
- 2017 年 7 月
- 2017 年 6 月
- 2017 年 5 月
- 2017 年 4 月
- 2017 年 3 月
- 2017 年 2 月
- 2017 年 1 月
- 2016 年 12 月
- 2016 年 11 月
- 2016 年 10 月
- 2016 年 9 月
- 2016 年 8 月
- 2016 年 7 月
- 2016 年 6 月
- 2016 年 5 月
- 2016 年 4 月
- 2016 年 3 月
- 2016 年 2 月
- 2016 年 1 月
- 2015 年 12 月
- 2015 年 11 月
- 2015 年 10 月
- 2015 年 9 月
- 2015 年 8 月
- 2015 年 7 月
- 2015 年 6 月
- 2015 年 5 月
- 2015 年 4 月
- 2015 年 3 月
- 2015 年 2 月
- 2015 年 1 月
- 2014 年 12 月
- 2014 年 11 月
- 2014 年 10 月
- 2014 年 9 月
- 2014 年 8 月
- 2014 年 7 月
- 2014 年 6 月
- 2014 年 5 月
- 2014 年 4 月
- 2014 年 3 月
- 2014 年 2 月
- 2014 年 1 月
- 2013 年 12 月
- 2013 年 11 月
- 2013 年 10 月
- 2013 年 9 月
- 2013 年 8 月
- 2013 年 7 月
- 2013 年 6 月
- 2013 年 5 月
- 2013 年 4 月
- 2013 年 3 月
- 2013 年 2 月
- 2013 年 1 月
- 2012 年 12 月
- 2012 年 11 月
- 2012 年 10 月
- 2011 年 12 月
分類
其他操作